Kinross – Tasiast West Branch Project
Delivered to the same operator throughout an eight-stage expansion program, the West Branch heap leach pad became one of the projects that shaped the team's institutional memory in West African conditions with an uninterrupted application period exceeding two years. Since the cell geometry and perimeter channels varied in each phase, panel layout and welding plans were generated from scratch at the beginning of each stage; a single…